A 50 kVA built for a cold store's start-up load

An apple cold store kept tripping an undersized supply. We sized, built and delivered a three-phase unit from the price guide.

Where
Shopian
Rating
50 kVA
Phase
Three phase
Price
As per guide

Sample content — replace before launch

01Brought in

The problem

Every time the compressors started together the existing transformer tripped, and the store could not hold temperature through the harvest intake.

02On the bench

What we found

The connected load had grown past the old unit's rating, and the compressor start-up surge pushed it over. A 50 kVA three-phase unit gave the headroom it needed.

03The work

What we did

  1. Listed every connected load with the owner and estimated the start-up surge

  2. Chose the rating from the published price guide and confirmed the input

  3. Built and tested the transformer at our Srinagar factory

  4. Delivered it and handed over the test record to the owner's electrician

A crowded machine workshop with lathes, tools and parts on every bench

04Outcome

The result

The store now starts its compressors without tripping and holds temperature through the intake season.

Rating
50 kVA
Phase
Three phase
Price
As per guide

Sample content — replace before launch

They explained exactly why the old transformer kept tripping before quoting for a new one. The price matched the guide, and the unit arrived when they said it would.

Cold-store operatorShopian · 50 kVA three phase